Natures Edge Buderim Stage 2

Stage 2 – Update

Stage 2 Civic works are well under way at Natures Edge Buderim.

The main storm water pipes located in the centre of the roads are currently being layed by our civil contractors, South East civil.

In the next few weeks the placement of the water mains will commence along the main access road into Stage 2.

All communication and electrical conduits and pits are on site and we are planning to have all these items placed within the next 3 weeks.

60% of all new sewerage works in this stage are now complete in readiness for construction to begin.Natures Edge Buderim Stage 2

 

Contractors are currently being finalized for the construction of our retaining walls and our lengthy acoustic fencing which will serve as a privacy screen and sound barrier for our new RV Homesites which will be constructed in Stage 2.